03-17 Community Hub Update

The construction site at 140 Joyce Avenue continues to be a busy place!
Have you had the chance to drive by? Here are a couple recent updates.

It's been a few weeks since we've had a peak inside the Hub building.

Progress on the apartment side includes insulation and installation of shower/bathtub fixtures.

The second story concrete floor has been poured on the Hub side and the walls are framed. The main stairway is built and the elevator lift shaft is framed, ready for installation.
Staging fills the entire multi-purpose room to enable the installation of duct work and the steel beams and framing for the room dividers above the ceiling.

We are still on schedule for August 1st occupancy!

The HUB common area

Front Door and Multi-Purpose Room from Outsode

Hallway

Minister's Office

Reception, Admin, Minister's Office

Support Beam for Multi-purpose Room dividers

Waiting Area - front foyer

Apartment Side of the HUB

Apartment

Apartment - Accessible bathroom

Elevator Shaft

This Community Hub project is a partnership between the John Howard Society of Southeastern New Brunswick and Visions United Church.